10/1/2003 to 9/30/2004
Activity Summary |
Other: | 56 |
Scouting: | 101 |
Trail Maintenance (PCT): | 2454 |
Training: | 166 |
Total Volunteer Hours: | 2777 |
Activity Detail (most recent on top) |
Project Date: | 9/29/2004 |
District: | Zig Zag Ranger District |
Leader: | Ron Goodwin |
Location: | Barlow Pass to Timberline Lodge |
Description: | Surveying PCT; measuring with a wheel. |
Volunteers |
Hours |
Goodwin, Katie | 9 |
Goodwin, Ron | 9 |
Project Total: 18 |
Project Date: | 9/26/2004 |
District: | Zig Zag Ranger District |
Leader: | Roberta Cobb |
Location: | Lolo Pass to Ramona Falls |
Description: | Surveying PCT; measuring with a wheel. |
Volunteers |
Hours |
Artman, Alan | 9 |
Cobb, Roberta | 9 |
Project Total: 18 |
Project Date: | 9/26/2004 |
District: | Zig Zag Ranger District |
Leader: | Kim Owen |
Location: | Sandy River Area |
Description: | Cleaned 25 drainage dips. |
Volunteers |
Hours |
Owen, Kim | 10 |
Owen, Pam | 10 |
Project Total: 20 |
Project Date: | 9/22/2004 |
District: | Hood River Ranger District |
Leader: | Roberta Cobb |
Location: | Barlow Pass to Wapinitia Pass |
Description: | Surveying PCT; measuring with a wheel. |
Volunteers |
Hours |
Artman, Alan | 10 |
Cobb, Roberta | 10 |
Project Total: 20 |
Project Date: | 9/12/2004 |
District: | Hood River Ranger District |
Leader: | Roberta Cobb |
Location: | Barlow Pass |
Description: | We replaced the temporary sign at the Barlow Pass trailhead (the previous temporary sign had been overwritten by a note to a hiker); we nailed in a new PCT emblem for southbound hikers (replacing one that has disappeared); and we cut away the large downed tree across the trail that was less than ¼ mile from the trailhead. |
Volunteers |
Hours |
Brown, Gary | 6 |
Brown, Maureen | 6 |
Cobb, Roberta | 5 |
Project Total: 17 |
Project Date: | 8/25/2004 |
District: | Zig Zag Ranger District |
Leader: | Ron Goodwin |
Location: | Barlow Pass toward Timberline Lodge |
Description: | Repired 30 drain dips and 12 log water bars. Brushed 2 miles. Removed berm from trail. Filled in low spots. |
Volunteers |
Hours |
Arkes, Bob | 10 |
Brown, Jerry | 9 |
Cather, Robert | 10 |
Gibson, Bus | 9 |
Goodwin, Katie | 9 |
Goodwin, Ron | 9 |
Hugo, Merrill | 10 |
Matson, Al | 9 |
Nelson, David | 9 |
Scovill, Wynne | 10 |
Sharp, Paul | 10 |
Project Total: 104 |
Project Date: | 8/21/2004 |
District: | Clackamas River Ranger District |
Leader: | John Wichman |
Location: | Breitenbush trailhead to Park Ridge |
Description: | Removed 2 trees, repaired numerous drain dips and 2 water bars. Numerous rocks and small boulders removed from the trail tread. |
Volunteers |
Hours |
Kitzhaber, Jim | 9 |
Kohler, Karen | 10 |
Marshall, Ron | 10 |
Morin, Michelle | 10 |
Wichman, John | 10 |
Project Total: 49 |
Project Date: | 8/6/2004 |
District: | Clackamas River Ranger District |
Leader: | Ernie Strahm |
Location: | Jude Lake to Breitenbush Lake |
Description: | Logged out 70 trees. Repaired slide damage near Breitenbush Lake. Repaired 5 drain dips, created 2 new drain dips. Brushed and performed tread maintenance. |
Volunteers |
Hours |
Cuerden, Becky | 19 |
Fisher, Jacqui | 19 |
Fisher, Jim | 19 |
Hutchison, Cindy | 14 |
Hutchison, Dewayne | 14 |
Hutchison, Seth | 14 |
Rivera, Austin | 14 |
Rivera, Carla | 14 |
Rivera, Keylee | 14 |
Rivera, Richard | 14 |
Robertson, Clyde | 19 |
Strahm, Ernie | 24 |
Strahm, Lori | 24 |
Ugrai, Miklos | 19 |
Welliver, Don | 19 |
Project Total: 260 |
Project Date: | 7/17/2004 |
District: | Zig Zag Ranger District |
Leader: | Kim Owen |
Location: | Sandy River to Paradise Park |
Description: | Cleaned 108 drain dips and 4 water bars. Repaired 1 slide and brushed for 100 yards. |
Volunteers |
Hours |
Babineaux, Richard | 7 |
Baker, Nathan | 11 |
Beard, Dennis | 11 |
Brown, Jerry | 11 |
Hilands, Bill | 11 |
Hughes, Heather | 7 |
Owen, Kim | 11 |
Ribble, Bonnie | 11 |
Ross, Bob | 11 |
Sharp, Paul | 11 |
Project Total: 102 |
Project Date: | 7/11/2004 |
District: | Columbia River Gorge |
Leader: | Roberta Cobb |
Location: | Herman Creek Trail Junction to Teakettle Springs |
Description: | Crew 1: Removed 6 logs, filled holes in trail, fixed 2 switchbacks, fixed sign at Teakettle Springs. Crew 2: Repaired 300' of trail, fixed a drainage dip, cleared 25' of poison oak. |
Volunteers |
Hours |
Arkes, Bob | 9 |
Brown, Gary | 9 |
Brown, Maureen | 9 |
Cobb, Roberta | 9 |
Vhay, John | 9 |
Winkler, Dan | 9 |
Project Total: 54 |
Project Date: | 7/10/2004 |
District: | Hood River Ranger District |
Leader: | Barb Adams |
Location: | Lolo Pass to Indian Springs Campground (7/10-11) |
Description: | Cleared logs. Filled four large holes. Moved debris and restored ditch. Repaired waterbar. |
Volunteers |
Hours |
Adams, Barb | 18 |
Adams, Dave | 18 |
Baker, Lynn | 10 |
Conners, Steve | 11 |
Gurnsey, Tiffany | 11 |
Hirigaray, Pam | 10 |
Kenny, Harold | 19 |
Lesowke, Linda | 11 |
Miller, Jeff | 10 |
Nelson, Lisa | 11 |
Peschke, Bunny | 11 |
Schotz, Lot | 12 |
Schotz, Pam | 12 |
Tucker, Deniece | 10 |
Project Total: 174 |
Project Date: | 7/10/2004 |
District: | Clackamas River Ranger District |
Leader: | David Roe |
Location: | Lemiti Meadows to Jude Lake |
Description: | Repaired numerous water bars and brushed huckleberry. |
Volunteers |
Hours |
Levy, Kathy | 7 |
Roe, David | 5 |
Roe, Eric | 5 |
Whitmyer, Dennis | 7 |
Project Total: 24 |
Project Date: | 7/10/2004 |
District: | Clackamas River Ranger District |
Leader: | Becky Wolf |
Location: | Jude Lake to Pinhead Buttes |
Description: | Logged out trees and brushed huckleberry and vine maple. |
Volunteers |
Hours |
Davis, Terrie | 7 |
Jones, Billy | 7 |
Jones, Guy | 7 |
Jones, Merlyn | 7 |
Lister, Norlene | 7 |
Scheele, Laura | 7 |
Project Total: 42 |
Project Date: | 7/10/2004 |
District: | Clackamas River Ranger District |
Leader: | Becky Wolf |
Location: | Timothy Lake area |
Description: | Repaired 15 water bars and brushed 2 miles of huckleberry and vine maple. |
Volunteers |
Hours |
Arnold, John | 7 |
Wolf, Becky | 7 |
Project Total: 14 |
Project Date: | 7/9/2004 |
District: | Clackamas River Ranger District |
Leader: | David Roe |
Location: | Lemiti Meadows to Warm Springs River |
Description: | Logged out 48 trees. Brushed huckleberry. |
Volunteers |
Hours |
Levy, Kathy | 12 |
Roe, David | 12 |
Roe, Eric | 13 |
Whitmyer, Dennis | 12 |
Project Total: 49 |
Project Date: | 7/9/2004 |
District: | Clackamas River Ranger District |
Leader: | Becky Wolf |
Location: | Road 42 to Warm Spring River |
Description: | Logged out 30 trees, repaired 38 water bars and brushed huckleberry and vine maple. |
Volunteers |
Hours |
Akers, Kay | 10 |
Arnold, John | 8 |
Beissmann, Angelika | 9 |
Beissmann, Pete | 9 |
DeVall, Dolores | 10 |
DeVall, Marty | 10 |
Peasley, Jack | 11 |
Peasley, Vicki | 11 |
Sischo, Gary | 10 |
Sischo, Peg | 10 |
Wolf, Becky | 11 |
Project Total: 109 |
Project Date: | 7/9/2004 |
District: | Clackamas River Ranger District |
Leader: | John Wichman |
Location: | Lodge Pole Trail and Pyramid Butte Bridge (7/9-11/04) |
Description: | Logged out 15 trees. Miscellaneous branch brushing and removal where direct trail impact. Pne day spent packing in material to the PCT Pyramid Butte bridge location for other to utilize during repair of bridge. |
Volunteers |
Hours |
McCloud, Charles | 21 |
Wichman, John | 21 |
Wichman, Sharon | 19 |
Project Total: 61 |
Project Date: | 7/9/2004 |
District: | Clackamas River Ranger District |
Leader: | Becky Wolf |
Location: | Jude Lake to Pinhead Buttes |
Description: | Logged out 29 trees. Brushed huckleberry and vine maple. |
Volunteers |
Hours |
Davis, Terrie | 10 |
Jones, Billy | 10 |
Jones, Guy | 10 |
Jones, Merlyn | 8 |
Latiolais, Paul | 9 |
Lister, Norlene | 10 |
Moore, Dorothy | 9 |
Moore, Mike | 9 |
Scheele, Laura | 10 |
Warren, Jack | 10 |
Project Total: 95 |
Project Date: | 7/7/2004 |
District: | Zig Zag Ranger District |
Leader: | Ron Goodwin |
Location: | Timberline Lodge to Barlow Pass |
Description: | Widened 600' of tread, filled in tread with sand in upper section (100'). Repaired drain dips and water bars. Replaced 1 sign. |
Volunteers |
Hours |
Allen, Eric | 10 |
Arkes, Bob | 10 |
Gibson, Bus | 9 |
Goodwin, Katie | 9 |
Goodwin, Ron | 9 |
Hammack, Brice | 11 |
McEver, Jim | 11 |
Nelson, David | 10 |
Sharp, Paul | 11 |
Vetter, Dick | 10 |
Project Total: 100 |
Project Date: | 7/1/2004 |
District: | Hood River Ranger District |
Leader: | John Vhay |
Location: | Wahtum Lake to Indian Springs Campground |
Description: | Logged out 13 trees. Brushed 100' of Beargrass |
Volunteers |
Hours |
Barnett, A. J. | 9 |
Vhay, John | 9 |
Project Total: 18 |
Project Date: | 6/30/2004 |
District: | Wind River Ranger District |
Leader: | Brice Hammack |
Location: | Wind River Ranger Station (Training Youth) |
Description: | Assisted in a trail maintenance work shop for Stevenson High School students under direction of Tom Linde of the USFS. Approximately 50 students working aon a mile of PCT. |
Volunteers |
Hours |
Gibson, Bus | 8 |
Goodwin, Ron | 8 |
Hammack, Brice | 8 |
Lukins, Dick | 8 |
Webb, Jim | 8 |
Project Total: 40 |
Project Date: | 6/26/2004 |
District: | Hood River Ranger District |
Leader: | John Vhay |
Location: | Wahtum Lake to Benson Plateau (2 days) |
Description: | Logged out 20 trees, cleaned 10 drain dips, repaired 4 slides, repaired 4 switchbacks (100'), removed major rock slabs from trail. Camped overnight at Benson Camp |
Volunteers |
Hours |
Allen, Eric | 19 |
Carr, Pete | 20 |
Foreman, Jim | 18 |
Foreman, Sue | 19 |
Gamroth, Dennis | 21 |
Gamroth, Sharon | 19 |
McLaughlin, Larry | 10 |
Nyberg, Carl | 19 |
Smith, Ron | 18 |
Vhay, John | 21 |
Project Total: 184 |
Project Date: | 6/26/2004 |
District: | Zig Zag Ranger District |
Leader: | Patty Carter |
Location: | Ramona Falls to Top Spur |
Description: | Logged out 16 trees. Removed limbs using pole saw south of Muddy Fork. |
Volunteers |
Hours |
Carter, Patty | 8 |
Goodwin, Katie | 7 |
Goodwin, Ron | 7 |
Szymkowski, Ken | 7 |
Project Total: 29 |
Project Date: | 6/19/2004 |
District: | Zig Zag Ranger District |
Leader: | Steve Plant |
Location: | Wapinitia Pass to Little Crater Lake |
Description: | Logged out 30 trees, repaired 6 drainage dips and 6 water bars, cleared one large root wad. |
Volunteers |
Hours |
Brown, Maureen | 13 |
Carr, Pete | 13 |
Castor, Linda | 13 |
Cobb, Roberta | 13 |
Langenderfer, Katrina | 13 |
Langenderfer, Steve | 13 |
Nyberg, Carl | 13 |
Plant, Steve | 13 |
Project Total: 104 |
Project Date: | 6/16/2004 |
District: | Columbia River Gorge |
Leader: | Chuck Martiny |
Location: | Gravel Pit to Carpenters Lake Trail Junction |
Description: | Logged out 14 small trees with hand saw. Cleaned 30 drain dips and 40 water bars. Repaired tread over 6 miles. |
Volunteers |
Hours |
Hammack, Brice | 13 |
Martiny, Chuck | 13 |
McLaughlin, Larry | 13 |
Murphy, Des | 13 |
Vetter, Dick | 13 |
Project Total: 65 |
Project Date: | 6/12/2004 |
District: | Zig Zag Ranger District |
Leader: | Kim Owen |
Location: | Sandy River area (2 days) |
Description: | Logged out 12 logs, repaired 16 drain dips, repaired 1 slide, loose rock cleared from Ramona Falls trailhead to Sandy guard station. Wing ditch system at Rushing Water Creek cleaned; sloughing and slide damage repaired. |
Volunteers |
Hours |
Barr, Austin | 12 |
Calkins, Robert | 13 |
Metke, Mike | 13 |
Olson, Charlie | 13 |
Olson, Rick | 13 |
Owen, Kim | 13 |
Owen, Pam | 13 |
Rossi, Philip | 13 |
Stadnik, Anj | 12 |
Streif, Cole | 12 |
Streif, David | 12 |
Tanous, Rick | 13 |
Yensen, Kermit | 12 |
Yensen, Zac | 12 |
Project Total: 176 |
Project Date: | 6/12/2004 |
District: | Hood River Ranger District |
Leader: | Patty Carter |
Location: | Lolo Pass to Top Spur |
Description: | Logged out 18 trees. |
Volunteers |
Hours |
Carter, Patty | 8 |
Martiny, Chuck | 8 |
Project Total: 16 |
Project Date: | 6/10/2004 |
District: | Zig Zag Ranger District |
Leader: | Ron Goodwin |
Location: | Barlow Pass to Timberline Lodge |
Description: | Removed 4 trees, cleaned 3 drainage dips, brushed 0.1 mile of trail, removed branches from 2.5 miles of trail. Scouting for 7/7 work party. |
Volunteers |
Hours |
Goodwin, Katie | 8 |
Goodwin, Ron | 8 |
Project Total: 16 |
Project Date: | 6/9/2004 |
District: | Columbia River Gorge |
Leader: | Larry McLaughlin |
Location: | Road 2070 to Three Corner Rock |
Description: | Logged out 10 trees with hand saws. Cleaned 200 drain dips. Repaired 150 fee of tread south of Three Corner Rock. |
Volunteers |
Hours |
Doty, Pat | 10 |
Hammack, Brice | 10 |
McLaughlin, Larry | 10 |
Murphy, Des | 10 |
Vetter, Dick | 10 |
Project Total: 50 |
Project Date: | 6/5/2004 |
District: | Zig Zag Ranger District |
Leader: | Patty Carter |
Location: | Ramona Falls to Top Spur |
Description: | Scouting. 14 trees to be logged out. |
Volunteers |
Hours |
Carter, Patty | 7 |
O'Neil, Geoff | 7 |
Project Total: 14 |
Project Date: | 6/2/2004 |
District: | Wind River Ranger District |
Leader: | Brice Hammack |
Location: | Sedum Ridge to Trout Creek |
Description: | Logged out 17 trees (one 30"). Cleaned many drain dips. Brushed for 4 miles. |
Volunteers |
Hours |
Hammack, Brice | 11 |
Martiny, Chuck | 11 |
Murphy, Des | 11 |
Vetter, Dick | 11 |
Webb, Jim | 11 |
Project Total: 55 |
Project Date: | 5/31/2004 |
District: | Hood River Ranger District |
Leader: | John Vhay |
Location: | Wahtum Lake |
Description: | Scouting to Camp Smokie. Many dangerous snags at the camp. Tread work needed for .5 mile on exposed east face of old burn area at mile 4 going north from Wahtum Lake. |
Volunteers |
Hours |
Gaston, Ernie | 10 |
Vhay, John | 10 |
Project Total: 20 |
Project Date: | 5/22/2004 |
District: | Zig Zag Ranger District |
Leader: | Kim Owen |
Location: | Ramona Falls to Paradise Park |
Description: | Scouting. 10 logs across trail up to 4700'. Small slough near wing dich at upper Sandy crossing and water dips. Snow at 4700'. |
Volunteers |
Hours |
Owen, Kim | 9 |
Project Total: 9 |
Project Date: | 5/20/2004 |
District: | Columbia River Gorge |
Leader: | Dick Lukins |
Location: | Highway 14 to Fort Rains |
Description: | Brushing with power brusher. Work to keep small streams in channel. Scouting around Three Corner Rock. |
Volunteers |
Hours |
Gouger, Gary | 8 |
Lukins, Dick | 10 |
Martiny, Chuck | 9 |
Project Total: 27 |
Project Date: | 5/19/2004 |
District: | Zig Zag Ranger District |
Leader: | Richard Walker |
Location: | Little Crater Lake to Road 42 |
Description: | Logged out 12 trees, cleaned 40 drain dips, brushed vine maple, performed minor tread repair and picked up litter. |
Volunteers |
Hours |
Hammack, Brice | 12 |
McLaughlin, Larry | 12 |
Vetter, Dick | 12 |
Walker, Penny | 12 |
Walker, Richard | 12 |
Project Total: 60 |
Project Date: | 5/13/2004 |
District: | Columbia River Gorge |
Leader: | Dick Lukins |
Location: | Cascade Locks area |
Description: | Met with Chuck Daughtry from Port of Cascade Locks to look over PCT on Port property, then over to Washington to slook at section of P CT that had been logged. |
Volunteers |
Hours |
Dawson, Mike | 7 |
Lukins, Dick | 7 |
Project Total: 14 |
Project Date: | 5/5/2004 |
District: | Wind River Ranger District |
Leader: | Larry McLaughlin |
Location: | Road 2070 to Sedum Ridge |
Description: | Logged out 6 trees, repaired 10 drain dips, 10 water bars, 2 slides and 1 rootwad. Brushed 20 sections (6' to 100'). Repaired 5 sections of tread (20' each). Created 30' wing ditch to handle seepage. |
Volunteers |
Hours |
Hammack, Brice | 11 |
McLaughlin, Larry | 11 |
Murphy, Des | 11 |
Vetter, Dick | 11 |
Webb, Jim | 10 |
Project Total: 54 |
Project Date: | 5/4/2004 |
District: | Columbia River Gorge |
Leader: | Dick Lukins |
Location: | Fort Rains to Bridge of the Gods |
Description: | Removed poison oak and cleared three drains. |
Volunteers |
Hours |
Hammack, Brice | 8 |
Lukins, Dick | 8 |
Project Total: 16 |
Project Date: | 5/1/2004 |
District: | Zig Zag Ranger District |
Leader: | Steve Queen |
Location: | Zig Zag Ranger Station (Chainsaw Certification) |
Description: | Six volunteers participated in a chainsaw re-certification course with the Zig Zag Ranger District. |
Volunteers |
Hours |
Cobb, Roberta | 9 |
McLaughlin, Larry | 9 |
Plant, Steve | 9 |
Queen, Steve | 9 |
Silfies, Dean | 9 |
Vhay, John | 9 |
Project Total: 54 |
Project Date: | 4/24/2004 |
District: | Wind River Ranger District |
Leader: | Brice Hammack |
Location: | Trout Creek to Carpenters Lake |
Description: | Scouting 4/24 and 4/25. |
Volunteers |
Hours |
Hammack, Brice | 23 |
Project Total: 23 |
Project Date: | 3/31/2004 |
District: | Columbia River Gorge |
Leader: | Dick Lukins |
Location: | Fort Rains to Bridge of the Gods |
Description: | Scouting north of Carpenters Lake. |
Volunteers |
Hours |
Lukins, Dick | 7 |
Martiny, Chuck | 7 |
Martiny, Karen | 7 |
Project Total: 21 |
Project Date: | 3/27/2004 |
District: | Wind River Ranger District |
Leader: | Steve Queen |
Location: | Wind River Ranger Station (Chainsaw Certification) |
Description: | Eight volunteers participated in a chainsaw re-certification course with the Wind River Ranger District. |
Volunteers |
Hours |
Adams, Dave | 9 |
Carter, Patty | 9 |
Goodwin, Ron | 9 |
Konner, Jack | 9 |
Lukins, Dick | 9 |
Martiny, Chuck | 9 |
Miller, Jeff | 9 |
Owen, Kim | 9 |
Project Total: 72 |
Project Date: | 3/24/2004 |
District: | Wind River Ranger District |
Leader: | Brice Hammack |
Location: | Panther Creek to Trout Creek |
Description: | Logged out 37 trees (75% snags, 25% green, average 13" in diameter). Cleaned water bars and brushed. |
Volunteers |
Hours |
Doty, Pat | 9 |
Hammack, Brice | 9 |
Vetter, Dick | 9 |
Walker, Richard | 9 |
Webb, Jim | 9 |
Project Total: 45 |
Project Date: | 3/14/2004 |
District: | Columbia River Gorge |
Leader: | Steve Queen |
Location: | Carpenters Lake Trail Junction to Fort Rains |
Description: | Logged out 10 trees, cleaned and repaired 50 drainage dips, repaired one slide area, brushed 100 feet, widened 1000 feet of tread, cleaned 3 bridges, cleaned wing ditches in 2 locations, and raked fir boughs. |
Volunteers |
Hours |
Allen, Eric | 12 |
Beard, Dennis | 12 |
Hovin, Leif | 7 |
Matson, Al | 12 |
Nemchick, Hal | 12 |
Owen, Kim | 12 |
Owen, Pam | 12 |
Queen, Steve | 11 |
Schaefer, Kary | 7 |
Simmons, Jessie | 12 |
Waxman, Andy | 12 |
Project Total: 121 |
Project Date: | 3/13/2004 |
District: | Columbia River Gorge |
Leader: | Steve Queen |
Location: | Bridge of the Gods to Hatfield Wilderness Boundary |
Description: | Logged out 15 trees (a 40" one was trimmed to allow equestrian passage), 50 drainage dips, 100 feet of tread widening, 500 feet of miscellaneous rock removal and treak resurfacing, cleaned Dry Creek bridge. |
Volunteers |
Hours |
Basque, Andy | 12 |
Cobb, Dave | 7 |
Cobb, Roberta | 12 |
Feldhaus, Joseph | 12 |
Gamer, Jeff | 12 |
Gamroth, Dennis | 12 |
Gamroth, Sharon | 12 |
Goodwin, Ron | 12 |
Johnson, Kris | 12 |
Kendoll, Jodi | 12 |
Moses, Cindy | 12 |
Queen, Steve | 11 |
Project Total: 138 |
Project Date: | 3/11/2004 |
District: | Columbia River Gorge |
Leader: | Dick Lukins |
Location: | Fort Rains to Bridge of the Gods |
Description: | Removed several small trees. Cleared five stream crossings. |
Volunteers |
Hours |
Lukins, Dick | 6 |
Project Total: 6 |