Project Date: 10/14/2004
Agency: Zig Zag Ranger District
Activity Type: Other
Leader: Brice Hammack
Location: Wapinitia Pass to Little Crater Lake
Description: Surveying PCT; measuring with a wheel.

Volunteers

Hours
Hammack, Brice 10
McLaughlin, Larry 10
Murphy, Des 10
Vetter, Dick 10

Project Total: 40

Project Date: 10/2/2004
Agency: Zig Zag Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Patty Carter
Location: Top Spour to Mount Hood Wilderness Boundary
Description: Logged out 1 tree, cleaned 5 drainage dips and 15 water bars.

Volunteers

Hours
Carter, Patty 10
Konner, Jack 10
O'Neil, Geoff 10

Project Total: 30

Project Date: 9/29/2004
Agency: Zig Zag Ranger District
Activity Type: Other
Leader: Ron Goodwin
Location: Barlow Pass to Timberline Lodge
Description: Surveying PCT; measuring with a wheel.

Volunteers

Hours
Goodwin, Katie 9
Goodwin, Ron 9

Project Total: 18

Project Date: 9/26/2004
Agency: Zig Zag Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Kim Owen
Location: Sandy River Area
Description: Cleaned 25 drainage dips.

Volunteers

Hours
Owen, Kim 10
Owen, Pam 10

Project Total: 20

Project Date: 9/26/2004
Agency: Zig Zag Ranger District
Activity Type: Other
Leader: Roberta Cobb
Location: Lolo Pass to Ramona Falls
Description: Surveying PCT; measuring with a wheel.

Volunteers

Hours
Artman, Alan 9
Cobb, Roberta 9

Project Total: 18

Project Date: 9/22/2004
Agency: Hood River Ranger District
Activity Type: Other
Leader: Roberta Cobb
Location: Barlow Pass to Wapinitia Pass
Description: Surveying PCT; measuring with a wheel.

Volunteers

Hours
Artman, Alan 10
Cobb, Roberta 10

Project Total: 20

Project Date: 9/12/2004
Agency: Hood River Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Roberta Cobb
Location: Barlow Pass
Description: We replaced the temporary sign at the Barlow Pass trailhead (the previous temporary sign had been overwritten by a note to a hiker); we nailed in a new PCT emblem for southbound hikers (replacing one that has disappeared); and we cut away the large downed tree across the trail that was less than ¼ mile from the trailhead.

Volunteers

Hours
Brown, Gary 6
Brown, Maureen 6
Cobb, Roberta 5

Project Total: 17

Project Date: 8/25/2004
Agency: Zig Zag Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Ron Goodwin
Location: Barlow Pass toward Timberline Lodge
Description: Repired 30 drain dips and 12 log water bars. Brushed 2 miles. Removed berm from trail. Filled in low spots.

Volunteers

Hours
Arkes, Bob 10
Brown, Jerry 9
Cather, Robert 10
Gibson, Bus 9
Goodwin, Katie 9
Goodwin, Ron 9
Hugo, Merrill 10
Matson, Al 9
Nelson, David 9
Scovill, Wynne 10
Sharp, Paul 10

Project Total: 104

Project Date: 8/21/2004
Agency: Clackamas River Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: John Wichman
Location: Breitenbush trailhead to Park Ridge
Description: Removed 2 trees, repaired numerous drain dips and 2 water bars. Numerous rocks and small boulders removed from the trail tread.

Volunteers

Hours
Kitzhaber, Jim 9
Kohler, Karen 10
Marshall, Ron 10
Morin, Michelle 10
Wichman, John 10

Project Total: 49

Project Date: 8/6/2004
Agency: Clackamas River Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Ernie Strahm
Location: Jude Lake to Breitenbush Lake
Description: Logged out 70 trees. Repaired slide damage near Breitenbush Lake. Repaired 5 drain dips, created 2 new drain dips. Brushed and performed tread maintenance.

Volunteers

Hours
Cuerden, Becky 19
Fisher, Jacqui 19
Fisher, Jim 19
Hutchison, Cindy 14
Hutchison, Dewayne 14
Hutchison, Seth 14
Rivera, Austin 14
Rivera, Carla 14
Rivera, Keylee 14
Rivera, Richard 14
Robertson, Clyde 19
Strahm, Ernie 24
Strahm, Lori 24
Ugrai, Miklos 19
Welliver, Don 19

Project Total: 260

Project Date: 7/17/2004
Agency: Zig Zag Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Kim Owen
Location: Sandy River to Paradise Park
Description: Cleaned 108 drain dips and 4 water bars. Repaired 1 slide and brushed for 100 yards.

Volunteers

Hours
Babineaux, Richard 7
Baker, Nathan 11
Beard, Dennis 11
Brown, Jerry 11
Hilands, Bill 11
Hughes, Heather 7
Owen, Kim 11
Ribble, Bonnie 11
Ross, Bob 11
Sharp, Paul 11

Project Total: 102

Project Date: 7/11/2004
Agency: Columbia River Gorge
Activity Type: Trail Maintenance (PCT)
Leader: Roberta Cobb
Location: Herman Creek Trail Junction to Teakettle Springs
Description: Crew 1: Removed 6 logs, filled holes in trail, fixed 2 switchbacks, fixed sign at Teakettle Springs. Crew 2: Repaired 300' of trail, fixed a drainage dip, cleared 25' of poison oak.

Volunteers

Hours
Arkes, Bob 9
Brown, Gary 9
Brown, Maureen 9
Cobb, Roberta 9
Vhay, John 9
Winkler, Dan 9

Project Total: 54

Project Date: 7/10/2004
Agency: Clackamas River Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: David Roe
Location: Lemiti Meadows to Jude Lake
Description: Repaired numerous water bars and brushed huckleberry.

Volunteers

Hours
Levy, Kathy 7
Roe, David 5
Roe, Eric 5
Whitmyer, Dennis 7

Project Total: 24

Project Date: 7/10/2004
Agency: Clackamas River Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Becky Wolf
Location: Jude Lake to Pinhead Buttes
Description: Logged out trees and brushed huckleberry and vine maple.

Volunteers

Hours
Davis, Terrie 7
Jones, Billy 7
Jones, Guy 7
Jones, Merlyn 7
Lister, Norlene 7
Scheele, Laura 7

Project Total: 42

Project Date: 7/10/2004
Agency: Clackamas River Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Becky Wolf
Location: Timothy Lake area
Description: Repaired 15 water bars and brushed 2 miles of huckleberry and vine maple.

Volunteers

Hours
Arnold, John 7
Wolf, Becky 7

Project Total: 14

Project Date: 7/10/2004
Agency: Hood River Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Barb Adams
Location: Lolo Pass to Indian Springs Campground (7/10-11)
Description: Cleared logs. Filled four large holes. Moved debris and restored ditch. Repaired waterbar.

Volunteers

Hours
Adams, Barb 18
Adams, Dave 18
Baker, Lynn 10
Conners, Steve 11
Gurnsey, Tiffany 11
Hirigaray, Pam 10
Kenny, Harold 19
Lesowke, Linda 11
Miller, Jeff 10
Nelson, Lisa 11
Peschke, Bunny 11
Schotz, Lot 12
Schotz, Pam 12
Tucker, Deniece 10

Project Total: 174

Project Date: 7/9/2004
Agency: Clackamas River Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: David Roe
Location: Lemiti Meadows to Warm Springs River
Description: Logged out 48 trees. Brushed huckleberry.

Volunteers

Hours
Levy, Kathy 12
Roe, David 12
Roe, Eric 13
Whitmyer, Dennis 12

Project Total: 49

Project Date: 7/9/2004
Agency: Clackamas River Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Becky Wolf
Location: Road 42 to Warm Spring River
Description: Logged out 30 trees, repaired 38 water bars and brushed huckleberry and vine maple.

Volunteers

Hours
Akers, Kay 10
Arnold, John 8
Beissmann, Angelika 9
Beissmann, Pete 9
DeVall, Dolores 10
DeVall, Marty 10
Peasley, Jack 11
Peasley, Vicki 11
Sischo, Gary 10
Sischo, Peg 10
Wolf, Becky 11

Project Total: 109

Project Date: 7/9/2004
Agency: Clackamas River Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: John Wichman
Location: Lodge Pole Trail and Pyramid Butte Bridge (7/9-11/04)
Description: Logged out 15 trees. Miscellaneous branch brushing and removal where direct trail impact. Pne day spent packing in material to the PCT Pyramid Butte bridge location for other to utilize during repair of bridge.

Volunteers

Hours
McCloud, Charles 21
Wichman, John 21
Wichman, Sharon 19

Project Total: 61

Project Date: 7/9/2004
Agency: Clackamas River Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Becky Wolf
Location: Jude Lake to Pinhead Buttes
Description: Logged out 29 trees. Brushed huckleberry and vine maple.

Volunteers

Hours
Davis, Terrie 10
Jones, Billy 10
Jones, Guy 10
Jones, Merlyn 8
Latiolais, Paul 9
Lister, Norlene 10
Moore, Dorothy 9
Moore, Mike 9
Scheele, Laura 10
Warren, Jack 10

Project Total: 95

Project Date: 7/7/2004
Agency: Zig Zag Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Ron Goodwin
Location: Timberline Lodge to Barlow Pass
Description: Widened 600' of tread, filled in tread with sand in upper section (100'). Repaired drain dips and water bars. Replaced 1 sign.

Volunteers

Hours
Allen, Eric 10
Arkes, Bob 10
Gibson, Bus 9
Goodwin, Katie 9
Goodwin, Ron 9
Hammack, Brice 11
McEver, Jim 11
Nelson, David 10
Sharp, Paul 11
Vetter, Dick 10

Project Total: 100

Project Date: 7/1/2004
Agency: Hood River Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: John Vhay
Location: Wahtum Lake to Indian Springs Campground
Description: Logged out 13 trees. Brushed 100' of Beargrass

Volunteers

Hours
Barnett, A. J. 9
Vhay, John 9

Project Total: 18

Project Date: 6/30/2004
Agency: Wind River Ranger District
Activity Type: Training
Leader: Brice Hammack
Location: Wind River Ranger Station (Training Youth)
Description: Assisted in a trail maintenance work shop for Stevenson High School students under direction of Tom Linde of the USFS. Approximately 50 students working aon a mile of PCT.

Volunteers

Hours
Gibson, Bus 8
Goodwin, Ron 8
Hammack, Brice 8
Lukins, Dick 8
Webb, Jim 8

Project Total: 40

Project Date: 6/26/2004
Agency: Hood River Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: John Vhay
Location: Wahtum Lake to Benson Plateau (2 days)
Description: Logged out 20 trees, cleaned 10 drain dips, repaired 4 slides, repaired 4 switchbacks (100'), removed major rock slabs from trail. Camped overnight at Benson Camp

Volunteers

Hours
Allen, Eric 19
Carr, Pete 20
Foreman, Jim 18
Foreman, Sue 19
Gamroth, Dennis 21
Gamroth, Sharon 19
McLaughlin, Larry 10
Nyberg, Carl 19
Smith, Ron 18
Vhay, John 21

Project Total: 184

Project Date: 6/26/2004
Agency: Zig Zag Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Patty Carter
Location: Ramona Falls to Top Spur
Description: Logged out 16 trees. Removed limbs using pole saw south of Muddy Fork.

Volunteers

Hours
Carter, Patty 8
Goodwin, Katie 7
Goodwin, Ron 7
Szymkowski, Ken 7

Project Total: 29

Project Date: 6/19/2004
Agency: Zig Zag Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Steve Plant
Location: Wapinitia Pass to Little Crater Lake
Description: Logged out 30 trees, repaired 6 drainage dips and 6 water bars, cleared one large root wad.

Volunteers

Hours
Brown, Maureen 13
Carr, Pete 13
Castor, Linda 13
Cobb, Roberta 13
Langenderfer, Katrina 13
Langenderfer, Steve 13
Nyberg, Carl 13
Plant, Steve 13

Project Total: 104

Project Date: 6/16/2004
Agency: Columbia River Gorge
Activity Type: Trail Maintenance (PCT)
Leader: Chuck Martiny
Location: Gravel Pit to Carpenters Lake Trail Junction
Description: Logged out 14 small trees with hand saw. Cleaned 30 drain dips and 40 water bars. Repaired tread over 6 miles.

Volunteers

Hours
Hammack, Brice 13
Martiny, Chuck 13
McLaughlin, Larry 13
Murphy, Des 13
Vetter, Dick 13

Project Total: 65

Project Date: 6/12/2004
Agency: Zig Zag Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Kim Owen
Location: Sandy River area (2 days)
Description: Logged out 12 logs, repaired 16 drain dips, repaired 1 slide, loose rock cleared from Ramona Falls trailhead to Sandy guard station. Wing ditch system at Rushing Water Creek cleaned; sloughing and slide damage repaired.

Volunteers

Hours
Barr, Austin 12
Calkins, Robert 13
Metke, Mike 13
Olson, Charlie 13
Olson, Rick 13
Owen, Kim 13
Owen, Pam 13
Rossi, Philip 13
Stadnik, Anj 12
Streif, Cole 12
Streif, David 12
Tanous, Rick 13
Yensen, Kermit 12
Yensen, Zac 12

Project Total: 176

Project Date: 6/12/2004
Agency: Hood River Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Patty Carter
Location: Lolo Pass to Top Spur
Description: Logged out 18 trees.

Volunteers

Hours
Carter, Patty 8
Martiny, Chuck 8

Project Total: 16

Project Date: 6/10/2004
Agency: Zig Zag Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Ron Goodwin
Location: Barlow Pass to Timberline Lodge
Description: Removed 4 trees, cleaned 3 drainage dips, brushed 0.1 mile of trail, removed branches from 2.5 miles of trail. Scouting for 7/7 work party.

Volunteers

Hours
Goodwin, Katie 8
Goodwin, Ron 8

Project Total: 16

Project Date: 6/9/2004
Agency: Columbia River Gorge
Activity Type: Trail Maintenance (PCT)
Leader: Larry McLaughlin
Location: Road 2070 to Three Corner Rock
Description: Logged out 10 trees with hand saws. Cleaned 200 drain dips. Repaired 150 fee of tread south of Three Corner Rock.

Volunteers

Hours
Doty, Pat 10
Hammack, Brice 10
McLaughlin, Larry 10
Murphy, Des 10
Vetter, Dick 10

Project Total: 50

Project Date: 6/5/2004
Agency: Zig Zag Ranger District
Activity Type: Scouting
Leader: Patty Carter
Location: Ramona Falls to Top Spur
Description: Scouting. 14 trees to be logged out.

Volunteers

Hours
Carter, Patty 7
O'Neil, Geoff 7

Project Total: 14

Project Date: 6/2/2004
Agency: Wind River Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Brice Hammack
Location: Sedum Ridge to Trout Creek
Description: Logged out 17 trees (one 30"). Cleaned many drain dips. Brushed for 4 miles.

Volunteers

Hours
Hammack, Brice 11
Martiny, Chuck 11
Murphy, Des 11
Vetter, Dick 11
Webb, Jim 11

Project Total: 55

Project Date: 5/31/2004
Agency: Hood River Ranger District
Activity Type: Scouting
Leader: John Vhay
Location: Wahtum Lake
Description: Scouting to Camp Smokie. Many dangerous snags at the camp. Tread work needed for .5 mile on exposed east face of old burn area at mile 4 going north from Wahtum Lake.

Volunteers

Hours
Gaston, Ernie 10
Vhay, John 10

Project Total: 20

Project Date: 5/22/2004
Agency: Zig Zag Ranger District
Activity Type: Scouting
Leader: Kim Owen
Location: Ramona Falls to Paradise Park
Description: Scouting. 10 logs across trail up to 4700'. Small slough near wing dich at upper Sandy crossing and water dips. Snow at 4700'.

Volunteers

Hours
Owen, Kim 9

Project Total: 9

Project Date: 5/20/2004
Agency: Columbia River Gorge
Activity Type: Trail Maintenance (PCT)
Leader: Dick Lukins
Location: Highway 14 to Fort Rains
Description: Brushing with power brusher. Work to keep small streams in channel. Scouting around Three Corner Rock.

Volunteers

Hours
Gouger, Gary 8
Lukins, Dick 10
Martiny, Chuck 9

Project Total: 27

Project Date: 5/19/2004
Agency: Zig Zag Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Richard Walker
Location: Little Crater Lake to Road 42
Description: Logged out 12 trees, cleaned 40 drain dips, brushed vine maple, performed minor tread repair and picked up litter.

Volunteers

Hours
Hammack, Brice 12
McLaughlin, Larry 12
Vetter, Dick 12
Walker, Penny 12
Walker, Richard 12

Project Total: 60

Project Date: 5/13/2004
Agency: Columbia River Gorge
Activity Type: Scouting
Leader: Dick Lukins
Location: Cascade Locks area
Description: Met with Chuck Daughtry from Port of Cascade Locks to look over PCT on Port property, then over to Washington to slook at section of P CT that had been logged.

Volunteers

Hours
Dawson, Mike 7
Lukins, Dick 7

Project Total: 14

Project Date: 5/5/2004
Agency: Wind River Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Larry McLaughlin
Location: Road 2070 to Sedum Ridge
Description: Logged out 6 trees, repaired 10 drain dips, 10 water bars, 2 slides and 1 rootwad. Brushed 20 sections (6' to 100'). Repaired 5 sections of tread (20' each). Created 30' wing ditch to handle seepage.

Volunteers

Hours
Hammack, Brice 11
McLaughlin, Larry 11
Murphy, Des 11
Vetter, Dick 11
Webb, Jim 10

Project Total: 54

Project Date: 5/4/2004
Agency: Columbia River Gorge
Activity Type: Trail Maintenance (PCT)
Leader: Dick Lukins
Location: Fort Rains to Bridge of the Gods
Description: Removed poison oak and cleared three drains.

Volunteers

Hours
Hammack, Brice 8
Lukins, Dick 8

Project Total: 16

Project Date: 5/1/2004
Agency: Zig Zag Ranger District
Activity Type: Training
Leader: Steve Queen
Location: Zig Zag Ranger Station (Chainsaw Certification)
Description: Six volunteers participated in a chainsaw re-certification course with the Zig Zag Ranger District.

Volunteers

Hours
Cobb, Roberta 9
McLaughlin, Larry 9
Plant, Steve 9
Queen, Steve 9
Silfies, Dean 9
Vhay, John 9

Project Total: 54

Project Date: 4/24/2004
Agency: Wind River Ranger District
Activity Type: Scouting
Leader: Brice Hammack
Location: Trout Creek to Carpenters Lake
Description: Scouting 4/24 and 4/25.

Volunteers

Hours
Hammack, Brice 23

Project Total: 23

Project Date: 3/31/2004
Agency: Columbia River Gorge
Activity Type: Scouting
Leader: Dick Lukins
Location: Fort Rains to Bridge of the Gods
Description: Scouting north of Carpenters Lake.

Volunteers

Hours
Lukins, Dick 7
Martiny, Chuck 7
Martiny, Karen 7

Project Total: 21

Project Date: 3/27/2004
Agency: Wind River Ranger District
Activity Type: Training
Leader: Steve Queen
Location: Wind River Ranger Station (Chainsaw Certification)
Description: Eight volunteers participated in a chainsaw re-certification course with the Wind River Ranger District.

Volunteers

Hours
Adams, Dave 9
Carter, Patty 9
Goodwin, Ron 9
Konner, Jack 9
Lukins, Dick 9
Martiny, Chuck 9
Miller, Jeff 9
Owen, Kim 9

Project Total: 72

Project Date: 3/24/2004
Agency: Wind River Ranger District
Activity Type: Trail Maintenance (PCT)
Leader: Brice Hammack
Location: Panther Creek to Trout Creek
Description: Logged out 37 trees (75% snags, 25% green, average 13" in diameter). Cleaned water bars and brushed.

Volunteers

Hours
Doty, Pat 9
Hammack, Brice 9
Vetter, Dick 9
Walker, Richard 9
Webb, Jim 9

Project Total: 45

Project Date: 3/14/2004
Agency: Columbia River Gorge
Activity Type: Trail Maintenance (PCT)
Leader: Steve Queen
Location: Carpenters Lake Trail Junction to Fort Rains
Description: Logged out 10 trees, cleaned and repaired 50 drainage dips, repaired one slide area, brushed 100 feet, widened 1000 feet of tread, cleaned 3 bridges, cleaned wing ditches in 2 locations, and raked fir boughs.

Volunteers

Hours
Allen, Eric 12
Beard, Dennis 12
Hovin, Leif 7
Matson, Al 12
Nemchick, Hal 12
Owen, Kim 12
Owen, Pam 12
Queen, Steve 11
Schaefer, Kary 7
Simmons, Jessie 12
Waxman, Andy 12

Project Total: 121

Project Date: 3/13/2004
Agency: Columbia River Gorge
Activity Type: Trail Maintenance (PCT)
Leader: Steve Queen
Location: Bridge of the Gods to Hatfield Wilderness Boundary
Description: Logged out 15 trees (a 40" one was trimmed to allow equestrian passage), 50 drainage dips, 100 feet of tread widening, 500 feet of miscellaneous rock removal and treak resurfacing, cleaned Dry Creek bridge.

Volunteers

Hours
Basque, Andy 12
Cobb, Dave 7
Cobb, Roberta 12
Feldhaus, Joseph 12
Gamer, Jeff 12
Gamroth, Dennis 12
Gamroth, Sharon 12
Goodwin, Ron 12
Johnson, Kris 12
Kendoll, Jodi 12
Moses, Cindy 12
Queen, Steve 11

Project Total: 138

Project Date: 3/11/2004
Agency: Columbia River Gorge
Activity Type: Trail Maintenance (PCT)
Leader: Dick Lukins
Location: Fort Rains to Bridge of the Gods
Description: Removed several small trees. Cleared five stream crossings.

Volunteers

Hours
Lukins, Dick 6

Project Total: 6