Volunteer Projects — Pacific Crest Trail Association
Hood River Ranger District
10/1/2005 to 9/30/2006
Activity Summary |
Trail Maintenance (PCT): | 539 |
Total Volunteer Hours: | 539 |
Activity Detail (most recent on top) |
Project Date: | 9/27/2006 |
District: | Hood River Ranger District |
Leader: | Barb Adams |
Location: | Wahtum Lake to Buck Peak |
Description: | Removed 5 trees and cleaned dozens of drain dips. |
Volunteers |
Hours |
Adams, Barb | 12 |
Adams, Dave | 12 |
Project Total: 24 |
Project Date: | 7/26/2006 |
District: | Hood River Ranger District |
Leader: | Brice Hammack |
Location: | Lolo Pass to 5.5 miles north |
Description: | Cleared 1 tree. Cleaned drainage dips and spot brushing. |
Volunteers |
Hours |
Doty, Pat | 10 |
Hammack, Brice | 10 |
McLaughlin, Larry | 10 |
Murphy, Des | 10 |
Project Total: 40 |
Project Date: | 7/2/2006 |
District: | Hood River Ranger District |
Leader: | Barb Adams |
Location: | Lolo Pass north for one mile |
Description: | Cleared one tree, claned drain dips, spot brushing. |
Volunteers |
Hours |
Adams, Barb | 4 |
McKinstry, Mindy | 5 |
Peinar, Carol | 6 |
Reed, Marge | 6 |
Project Total: 21 |
Project Date: | 6/26/2006 |
District: | Hood River Ranger District |
Leader: | Barb Adams |
Location: | Lolo Pass to Hatfield Wilderness boundary |
Description: | Cleared 28 trees. |
Volunteers |
Hours |
Adams, Barb | 36 |
Adams, Dave | 36 |
Tucker, Deniece | 11 |
Project Total: 83 |
Project Date: | 6/26/2006 |
District: | Hood River Ranger District |
Leader: | John Vhay |
Location: | Wahtum Lake to Camp Smokey |
Description: | Cleared 40 trees, repaired 400' side hill sough and 2 root wads, rebuilt 100' of new switch back. |
Volunteers |
Hours |
Arkes, Bob | 24 |
Cather, Robert | 27 |
Logan, Kathy | 20 |
Murray, Michael | 27 |
Smith, Ron | 25 |
Vhay, John | 25 |
Vhay, Tom | 25 |
Project Total: 173 |
Project Date: | 6/17/2006 |
District: | Hood River Ranger District |
Leader: | Roberta Cobb |
Location: | Barllow Pass to Frog Lake |
Description: | Cleared 19 trees and cleaned many drain dips. Repaired tread 1/4 mile thorough; 1 mile spot fixes. |
Volunteers |
Hours |
Allen, Eric | 9 |
Cobb, Roberta | 9 |
Hanes, Douglas | 9 |
Kaai, Robin | 11 |
Matson, Al | 9 |
Merrifield, John | 9 |
Ranganathan, Nandini | 9 |
Weston, Ruth | 9 |
White, Hal | 9 |
Winkler, Dan | 9 |
Project Total: 92 |
Project Date: | 6/10/2006 |
District: | Hood River Ranger District |
Leader: | John Vhay |
Location: | Wahtum Lake |
Description: | Cleared 11 logs -- 2 (36"), 4 (20-24") and 5 (<20"). Cleaned wing ditches and trail drains. |
Volunteers |
Hours |
Allen, Eric | 9 |
Arkes, Bob | 8 |
Carr, Pete | 10 |
Doty, Pat | 10 |
Murphy, Des | 10 |
Regehr, Don | 10 |
Silfies, Dean | 10 |
Thompson, Bob | 9 |
Vhay, John | 10 |
Project Total: 86 |
Project Date: | 5/21/2006 |
District: | Hood River Ranger District |
Leader: | Roberta Cobb |
Location: | Frog Lake to beyond Twin Lakes junction |
Description: | Cleared 26 logs. |
Volunteers |
Hours |
Allen, Eric | 10 |
Cobb, Roberta | 10 |
Project Total: 20 |