Activity Summary

Trail Maintenance (PCT): 361


Total Volunteer Hours: 361

Activity Detail (most recent on top)

Project Date: 7/22/2010 to 7/24/2010
Agency: Hood River Ranger District
Leader: John Vhay
Location: Indian Springs to Indian Mountain
Description: Cleaned 6 drain dips. Brushed and repaired tread on 1000' of trail. Constructred 180 feet of rock retaining wall on both sides of trail and 220 feet of single (uphill) retaining wall per Ken Kollas.

Volunteers

Hours
Barnett, AJ 11
Donovan, Katie 11
Hopkins, Levi 11
Koppy, Larry 20
Melander, David 26
Miller, Garth 11
Nanson, Sarah 11
Regehr, Don 11
Vhay, John 26

Project Total: 138

Project Date: 7/15/2010 to 7/17/2010
Agency: Hood River Ranger District
Leader: John Vhay
Location: Indian Springs to Indian Mountain
Description: Cleaned 4 drain dips and 3 water bars. Rebuilt 100 feet of tread installing 3 feet of retaining rock wall and lower wall to hold tread. Filled trail and compacted soil. Decommissioned illegal campsites at Wahtum Lake.

Volunteers

Hours
Hanes, Douglas 21
Squires, Bob 9
Vhay, John 21

Project Total: 51

Project Date: 6/20/2010
Agency: Hood River Ranger District
Leader: Roberta Cobb
Location: Barlow Pass south
Description: Logged out 25 trees (5: B logs, 20 A logs).

Volunteers

Hours
Caldwell, Robert 8
Cobb, Roberta 12
Covey, Kathy 9
Hanes, Douglas 8
Koppy, Larry 10
Mater, James 8
McKinstry, Mindy 8
Ranganathan, Nandini 8

Project Total: 71

Project Date: 5/23/2010
Agency: Hood River Ranger District
Leader: Roberta Cobb
Location: Frog Lake north
Description: Logged out 3 trees (2 A on the PCT and 1 B on the Twin Lakes Trail).

Volunteers

Hours
Ames, Julie 5
Cobb, Roberta 6

Project Total: 11

Project Date: 5/17/2010
Agency: Hood River Ranger District
Leader: Roberta Cobb
Location: Frog Lake north
Description: Logged out 7 trees (6 A size, 1 small B)

Volunteers

Hours
Brown, Maureen 6
Cobb, Roberta 6
Neitch, Ulli 6

Project Total: 18

Project Date: 10/4/2009
Agency: Hood River Ranger District
Leader: Roberta Cobb
Location: Frog Lake north
Description: Repaired many drain dips, light brushing and slough removal for 3 miles.

Volunteers

Hours
Booth, Jeff 9
Bunting, Clint 9
Carr, Pete 9
Cather, Robert 9
Cobb, Roberta 8
Covey, Kathy 10
Dolinar, Brian 9
Spartis, Diana 9

Project Total: 72